Exxon Mobil successfully proposed numerous changes to a Texas laboratory's report on the cause of the Pegasus pipeline's 2013 rupture in Mayflower, even though the oil giant described the company as "independent," according to newly unsealed documents in a class-action lawsuit.
Document set
Mayflower oil spill
- ExxonMobil final downstream data assessment report
- Central Arkansas Water letter to PHMSA
- Rudy Webb, et al v. Exxon Mobil Corporation briefing
- Exxon's response to Central Arkansas Water
- Central Arkansas Water letter to Judge Baker
- Exxon Mobil complaint
- Exxon Mobil consent decree
- Exxon Mobil Federal Agency Report
- Exxon responds to motion to disclose all oil spill docs
- Plantiffs' motion to Exxon Mobil
- Exxon Mobil petition
- Exxon Mobil remedial work plan proposal
- Exxon Mobil responds to lawsuit
- Mobil Pipeline Company respond to lawsuit
- Accufacts Major Issues Memo
- ExxonMobil Environmental Services Co. mitigation action plan
- Exxon Mobil's Pegasus pipeline remedial work plan
- PHMSA approves Exxon Mobil's plan to reopen part of Pegasus pipeline
- ExxonMobil DADAR report, revision 5
- ADEQ comments on ExxonMobil's final report
- Exxon fact sheet on Pegasus pipeline segments
- Downstream Areas Data Assessment Report
- Responses to ADEQ Comments
- Sheen monitoring report no. 8
- PHMSA responds to ADH letter
- June 3 letter from ADH to PHMSA, EMPCO
- ExxonMobil hearing request
- Letter: Griffin opposed to restarting Pegasus pipeline
- Pipeline and Hazardous Materials Safety Administration updated report on Exxon spill
- ExxonMobil $2.6 million fine
- Rep. Griffin responds to McDaniel's letter
- McDaniel's letter to Rep. Griffin
- Mayflower mayor statement on spill 6 months later
- Confidentiality agreement between Exxon, CAW
- Notice of intent to file civil suit against ExxonMobil, PHMSA
- CAW's notice of intent letter to Arkansas officials
- Tim Griffin letter to Exxon Mobil
- Letter from ExxonMobil president
- ExxonMobil emergency response plan request letter
- Central Ark. Water 2010 letter to PHMSA
- 2010 Pipeline report: Doniphan-Conway
- 2010 Pipeline report: Conway-Corsicana (Part 4)
- 2010 Pipeline report: Conway-Corsicana (Part 3)
- 2010 Pipeline report: Conway-Corsicana (Part 2)
- 2010 Pipeline report: Conway-Corsicana (Part 1)
- Oil spill pressure test, Section 21
- Oil spill pressure test, Section 8
- Oil spill pressure test, Section 15
- Oil spill pressure test, Section 1
- Mayflower oil spill: Metallurgical report
- Pryor, Boozman, Griffin oil spill letter
- ExxonMobil responds to Arkansas officials
- Exxon Mobil's response to Rep. Markey letter
- Pipeline and Hazardous Materials Safety Administration response to Rep. Markey letter
- Rep. Markey letter to Exxon
- Rep. Markey letter to Pipeline and Hazardous Materials Safety Administration
- Class-action suit against Exxon Mobil
- U.S.-Arkansas complaint against Exxon Mobil
- Exxon property purchase program
- Mayflower oil spill: Federal Corrective Action Order
- Mayflower oil spill clean-up response draft
- Mayflower oil spill: Exxon status maps for April 3-4
- Mayflower oil spill: April 4 cleanup assignments
- Mayflower oil spill: Wildlife task force assignments for April 3
- Mayflower oil spill: EPA report for April 2
- Mayflower oil spill: EPA report for April 3
- Mayflower oil spill: EPA report for April 4
- Mayflower oil spill: EPA report for April 7
- Mayflower oil spill: EPA report for March 31
- Mayflower oil spill: EPA report for April 1
- Mayflower oil spill: Incident status summary
- Mayflower oil spill: Wabasca heavy crude oil data
- Mayflower oil spill: Sampling and analysis plan
- Mayflower oil spill: Waste disposal plan
- Mayflower oil spill: Homeowner re-entry plan
- Mayflower oil spill: EPA report for March 30
- Lawsuit filed against Exxon Mobil in Mayflower oil spill
"The court has unsealed documents showing that the report was not independent as Exxon had claimed," Marcus Bozeman, an attorney for the plaintiffs, said Monday.
Exxon Mobil spokesman Christian Flathman said in an email that the company "respects the court's decision to make these files public."
Flathman defended the proposed changes -- many of which were accepted and incorporated into the final report released to the public -- as suggested "improvements" made with a federal regulatory agency's knowledge.
The disclosure appears in two of 31 documents that U.S. District Judge Brian Miller ordered unsealed after Exxon Mobil fought to keep them confidential. Other documents, including four that the lawsuit's plaintiffs specifically requested to be unsealed, remain confidential. The unsealed documents were added to the court's website late Friday evening.
One document is an email dated July 3, 2013, from Thad Massingale, a representative of Exxon Mobil Corp. subsidiary Exxon Mobil Pipeline Co., to Hurst Metallurgical Research Laboratory and to the U.S. Transportation Department. In it, Massingale proposes "edits" to the laboratory's final report and to related photograph captions.
The proposed edits include deletions of material, as well as changes and additions.
One week after that email, on July 10, 2013, Exxon Mobil released a statement to the news media summarizing the report's chief findings and calling the laboratory "independent."
The Pipeline and Hazardous Materials Safety Administration, a part of the U.S. Transportation Department, eventually posted the final draft on its website.
Asked if the federal agency was aware of the oil giant's involvement in the report and if such participation was typical, safety administration spokesman Patricia Klinger said Monday that agency officials would need to consult with their legal office and would be "looking into" the matter.
The roughly 850-mile-long Pegasus pipeline, running from Texas' Gulf Coast to Patoka, Ill., cracked open in Mayflower's Northwoods subdivision on March 29, 2013, and spilled an estimated 210,000 gallons of heavy crude into the neighborhood. Most of the pipeline, including that portion in Arkansas, remains shut down.
Flathman said Exxon Mobil sent "the suggested improvements to the draft report" to the safety administration at the same time as it sent them to the laboratory in an effort "to enhance the report's focus and clarity, factual accuracy, and consistency of terminology."
"The independent testing lab was free to accept or reject the suggested improvements," and the safety administration "was provided the same opportunity for comment. PHMSA took no exception to the final report," he added.
Exxon Mobil's communications with the laboratory "were conducted in a manner that fully respected the independent nature of the lab's testing and analysis processes," he said.
Bozeman, however, said, "Whether or not PHMSA knew about Exxon's involvement in drafting the Hurst report, the fact remains that the report was not independent as Exxon claims."
Examples of changes that Exxon Mobil successfully proposed include a section about the manufacturing process for the kind of pipe used in the Pegasus, which was built in 1947-48 by a now-defunct Ohio company. That type of pipe is no longer made.
Other changes include repeatedly altering such words such as "cracked" to "fractured," or "cracks" to "splits," as well as many changes that simply appear to be writing preferences.
It was unclear why some documents ever were sealed. One, for instance, is an August 2013 Arkansas Times article about the pipeline and Arkansas residents who live along it.
Another unsealed document -- an accident report dated Oct. 23, 2013, that was prepared by the safety administration -- says Exxon Mobil failed to consider the pipeline's Mayflower segment as susceptible to seam failure at the time.
The agency publicly addressed the issue in a series of nine probable safety violations it released against Exxon Mobil in November 2013 -- a finding that included proposed fines totaling $2,659,200 that Exxon is appealing. But the accident report provides more details.
At one point, this unsealed document says, "The operator did not consider this segment of piping susceptible to seam failure and did not select a tool capable of determining the full spectrum of seam issues known to exist in the Pegasus Pipeline; therefore, the in-line inspections performed subsequent to the hydrotests [water-pressure tests] did not detect the defects that existed in the failed segment of line."
The safety administration also writes, "Contributing factors to the accident were the failure of the operator's integrity management program to identify the pipe as susceptible to seam failure, and failure of the operator to carry out integrity management actions appropriate to pipe with such characteristics."
In a separate document, the safety administration says Exxon Mobil "did not consider the line to be susceptible to seam failures because there were no in-service failures." Rather, it says, there were "only failures that occurred ... during hydrotesting of the pipeline" when the line was not transporting oil.
The safety administration says Exxon Mobil should have treated these hydrostatic test failures "as an indication of the susceptibility of seam failure, and identified this as a risk factor" in its integrity management program.
Bozeman said the safety administration's finding is "troublesome because of the age of the pipeline and the repeated warnings Exxon got from [a federal regulatory agency] over the years."
The pipeline company "continues to dispute these alleged violations through the administrative process," Flathman said.
He said the company did a hydrostatic, or water-pressure, test on the line "as recently as 2006."
The safety administration has cautioned the industry about such low-frequency electric-resistance-weld, or ERW, pipe since the 1980s. In 1988, regulators warned of 12 pipeline failures that occurred in 1986 and 1987 that involved such ERW pipe seams made before 1970. More warnings followed.
State Desk on 01/20/2015